Roadway Fill Volume Calculator

Estimate fill between two roadway sections with the average-end-area method.

Roadway Fill Volume Calculator

Cross-section model

Choose the cross-section model. Side slopes are included only in the embankment option.

Example: 100

Example: 24

Top width of the roadbed.

Example: 2

Example: 4

Material & hauling

Optional: enter a compaction allowance and truck capacity to estimate loose material and haul loads. Leave allowance blank to show compacted fill only.

%

Example: 20

Adds loose material above the calculated compacted fill.

Example: 14

Roadway fill results

Compacted fill volume
-- --
Average fill depth
--
Average cross-sectional area
--
Volume per linear foot
-- --
Roadway length
--
Roadway width
--
Depth at start
--
Depth at end
--
Loose fill to haul
--
Truck loads
--

The average-end-area method uses rectangular sections at the start and end.

Calculation details

Roadway fill results

Results

Average-end-area fill calculation

Choose rectangular sections for a simple fill estimate, or choose an embankment with side slopes to add the two side-slope triangles at each section. The calculator averages the start and end areas, then multiplies by the station distance.

The compacted result is the geometric in-place volume. The optional allowance adds material for loose delivery and truck-load planning; leave it blank when you only need compacted fill. Use geotechnical or project values when available.

This is a fill-only segment estimate. Separate cut, stripping, unsuitable excavation, topsoil, and material losses instead of netting them into one unverified number.

Use the road base calculator for a uniform aggregate layer, or the asphalt calculator for pavement tonnage above the prepared grade.

FAQ

How does the average-end-area method calculate fill?

It averages the fill cross-sectional areas at the start and end of a segment, then multiplies that average by the segment length.

How are roadway side slopes included?

Choose Embankment with side slopes to include the roadbed rectangle plus both side-slope triangles. Enter 2 for a slope of 2 horizontal to 1 vertical; Rectangular fill omits those triangles.

What does the compaction allowance do?

It converts the calculated compacted fill into a larger planning quantity for loose material and truck loads. It is optional and does not change compacted fill; leave it blank when you only need the geometric in-place volume.

Can this calculator handle several stations or cut sections?

This page calculates one fill segment between two sections. Calculate each fill-only segment separately when the profile has more stations, and keep cut and unsuitable material quantities separate.